Resource Over-allocation Alert Over-allocated
Alert #OA-2025-034 • Detected 10 Feb 2026 • Severity: High
RK
Rajesh Kumar
Total Allocation
120%
Over By
20%
Projects
2
Allocation Overview
Allocation Breakdown
| Project | Role | Duration | Allocation | Reducible | Notes |
|---|---|---|---|---|---|
|
PRJ-2025-001
Cipla R&D Lab Setup
|
Project Manager | Jan 2025 – Jun 2025 | 100% | Cannot Reduce | Critical project — sole PM assigned. Customer-facing role. |
|
PRJ-2025-005
Serum Institute BSL-3 Lab
|
Advisory PM | Mar 2025 – Dec 2025 | 20% | Reducible | Advisory role only. Can be reassigned to deputy PM. |
Conflict Timeline
Project
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Cipla R&D Lab
Serum BSL-3
Total Allocation
100%
100%
120%
120%
120%
120%
20%
20%
20%
20%
20%
20%
Overlap Period: March 2025 – June 2025 (4 months). Rajesh Kumar is allocated at 120% during this period, exceeding the 100% capacity threshold by 20%.