Project Schedule
Cipla R&D Lab Setup — PRJ-2025-001 • Master schedule with task hierarchy and progress tracking
22
Total Tasks
7
Completed
4
In Progress
11
Not Started
Overall Progress
38%
Baseline Comparison
Schedule – List View
| Task Name | Start | End | Duration | Progress | Predecessor | Assigned To | Status | |
|---|---|---|---|---|---|---|---|---|
|
Phase 1: Planning & Design
|
Jan 15 | Feb 15 | 32 days |
100%
|
— | — | Completed | |
|
1.1
Site Survey
|
Jan 15 | Jan 18 | 4 days |
100%
|
— |
RK
Rajesh Kumar
|
Completed |
|
|
1.2
Requirements Finalization
|
Jan 18 | Jan 25 | 7 days |
100%
|
1.1 FS |
PS
Priya Sharma
|
Completed |
|
|
1.3
Concept Design
|
Jan 25 | Feb 5 | 12 days |
100%
|
1.2 FS |
AP
Amit Patel
|
Completed |
|
|
1.4
Design Review & Approval
|
Feb 5 | Feb 15 | 10 days |
100%
|
1.3 FS |
RK
Rajesh Kumar
|
Completed |
|
|
Phase 2: Engineering Design
Critical Path
|
Feb 16 | Mar 31 | 44 days |
60%
|
Phase 1 | — | In Progress | |
|
2.1
Detailed Engineering Drawings
|
Feb 16 | Mar 10 | 23 days |
75%
|
1.4 FS |
AP
Amit Patel
|
In Progress |
|
|
2.2
TDS Preparation
|
Feb 20 | Mar 15 | 24 days |
50%
|
2.1 SS+4d |
PS
Priya Sharma
|
In Progress |
|
|
2.3
Drawing Review by Customer
|
Mar 10 | Mar 20 | 10 days |
0%
|
2.1 FS |
RK
Rajesh Kumar
|
Not Started |
|
|
2.4
Final Drawing Approval
|
Mar 20 | Mar 31 | 11 days |
0%
|
2.3 FS |
RK
Rajesh Kumar
|
Not Started |
|
|
Phase 3: Procurement & Manufacturing
|
Mar 15 | May 15 | 62 days |
10%
|
2.2 FS-5d | — | In Progress | |
|
3.1
PR Generation
|
Mar 15 | Mar 20 | 5 days |
100%
|
2.2 SS |
SN
Suresh Nair
|
Completed |
|
|
3.2
Vendor Selection & PO
|
Mar 20 | Apr 5 | 16 days |
0%
|
3.1 FS |
SN
Suresh Nair
|
Not Started |
|
|
3.3
Manufacturing
|
Apr 5 | May 10 | 35 days |
0%
|
3.2 FS |
DJ
Deepak Joshi
|
Not Started |
|
|
3.4
Factory Acceptance Test
|
May 10 | May 15 | 5 days |
0%
|
3.3 FS |
RK
Rajesh Kumar
|
Not Started |
|
|
Phase 4: Delivery & Installation
|
May 15 | Jun 10 | 27 days |
0%
|
Phase 3 | — | Not Started | |
|
4.1
Dispatch & Transit
|
May 15 | May 22 | 7 days |
0%
|
3.4 FS |
SN
Suresh Nair
|
Not Started |
|
|
4.2
Site Installation
|
May 22 | Jun 5 | 15 days |
0%
|
4.1 FS |
DJ
Deepak Joshi
|
Not Started |
|
|
4.3
Site Acceptance Test
|
Jun 5 | Jun 10 | 5 days |
0%
|
4.2 FS |
RK
Rajesh Kumar
|
Not Started |
|
|
Phase 5: Commissioning & Handover
|
Jun 10 | Jun 30 | 20 days |
0%
|
Phase 4 | — | Not Started | |
|
5.1
Services Connection & Testing
|
Jun 10 | Jun 18 | 8 days |
0%
|
4.3 FS |
DJ
Deepak Joshi
|
Not Started |
|
|
5.2
Training & Documentation
|
Jun 18 | Jun 25 | 7 days |
0%
|
5.1 FS |
PS
Priya Sharma
|
Not Started |
|
|
5.3
Final Handover & Sign-off
|
Jun 25 | Jun 30 | 5 days |
0%
|
5.2 FS |
RK
Rajesh Kumar
|
Not Started |
|
Showing 22 tasks across 5 phases
Completed
In Progress
Not Started
Critical Path