Milestone Dependency Mapping
PRJ-2025-001 — Cipla R&D Lab Setup • 6 Milestones • 7 Dependencies
Total Milestones
6
1 Completed, 1 In Progress, 4 Pending
Critical Path Length
122 days
Feb 28 → Jun 30, 2025
Valid Dependencies
5
of 7 total dependencies
At Risk
2
1 at risk, 1 broken link detected
Network Diagram
FS +0d
FS +5d
FS +3d
FS +0d
SS +0d
FS +0d
MS-001
Design Approval
28 Feb 2025
Completed
AP Amit Patel
MS-002
Material Order Placed
15 Mar 2025
In Progress
PS Priya Sharma
MS-003
Factory Acceptance Test
10 May 2025
Not Started
SN Suresh Nair
MS-004
Site Readiness Certification
15 May 2025
Not Started
VR Vikram Rao
MS-005
Installation Complete
15 Jun 2025
Not Started
SN Suresh Nair
MS-006
Handover & Commissioning
30 Jun 2025
Not Started
RK Rajesh Kumar
Legend:
Critical Path
Standard Dependency
Completed
In Progress
Not Started
FS = Finish-to-Start
SS = Start-to-Start
Dependency Details
| # | From Milestone | To Milestone | Type | Lag (days) | Status | Critical Path | |
|---|---|---|---|---|---|---|---|
| 1 | MS-001 Design Approval | MS-002 Material Order Placed | FS | 0 | Valid | Yes | |
| 2 | MS-001 Design Approval | MS-004 Site Readiness Cert. | FS | +5 | Valid | — | |
| 3 | MS-002 Material Order Placed | MS-003 Factory Acceptance Test | FS | +3 | At Risk | Yes | |
| 4 | MS-003 Factory Acceptance Test | MS-005 Installation Complete | FS | 0 | Valid | Yes | |
| 5 | MS-004 Site Readiness Cert. | MS-005 Installation Complete | SS | 0 | Valid | — | |
| 6 | MS-005 Installation Complete | MS-006 Handover & Commissioning | FS | 0 | Valid | Yes | |
| 7 | MS-002 Material Order Placed | MS-004 Site Readiness Cert. | FS | -2 | Broken | — |
Validation Results
No circular dependencies detected
All dependency chains resolve correctly without loops.
Dependency #3 (MS-002 → MS-003) at risk
MS-002 is currently delayed by 5 days. This may push MS-003 past its target date of 10 May 2025.
Dependency #7 (MS-002 → MS-004) is broken
Negative lag of -2 days creates an impossible schedule constraint. Lead time conflicts with MS-002 current progress. Consider removing this dependency or adjusting the lag.
Critical path is valid
MS-001 → MS-002 → MS-003 → MS-005 → MS-006 (122 days total)