Milestone Dependency Mapping
Total Milestones
6
1 Completed, 1 In Progress, 4 Pending
Critical Path Length
122 days
Feb 28 → Jun 30, 2025
Valid Dependencies
5
of 7 total dependencies
At Risk
2
1 at risk, 1 broken link detected

Network Diagram

FS +0d
FS +5d
FS +3d
FS +0d
SS +0d
FS +0d
MS-001
Design Approval
28 Feb 2025
Completed
AP Amit Patel
MS-002
Material Order Placed
15 Mar 2025
In Progress
PS Priya Sharma
MS-003
Factory Acceptance Test
10 May 2025
Not Started
SN Suresh Nair
MS-004
Site Readiness Certification
15 May 2025
Not Started
VR Vikram Rao
MS-005
Installation Complete
15 Jun 2025
Not Started
SN Suresh Nair
MS-006
Handover & Commissioning
30 Jun 2025
Not Started
RK Rajesh Kumar
Legend:
Critical Path
Standard Dependency
Completed
In Progress
Not Started
FS = Finish-to-Start
SS = Start-to-Start

Dependency Details

# From Milestone To Milestone Type Lag (days) Status Critical Path
1 MS-001 Design Approval MS-002 Material Order Placed FS 0 Valid Yes
2 MS-001 Design Approval MS-004 Site Readiness Cert. FS +5 Valid
3 MS-002 Material Order Placed MS-003 Factory Acceptance Test FS +3 At Risk Yes
4 MS-003 Factory Acceptance Test MS-005 Installation Complete FS 0 Valid Yes
5 MS-004 Site Readiness Cert. MS-005 Installation Complete SS 0 Valid
6 MS-005 Installation Complete MS-006 Handover & Commissioning FS 0 Valid Yes
7 MS-002 Material Order Placed MS-004 Site Readiness Cert. FS -2 Broken

Validation Results

Last validated: 12 Feb 2026, 2:30 PM
No circular dependencies detected
All dependency chains resolve correctly without loops.
Dependency #3 (MS-002 → MS-003) at risk
MS-002 is currently delayed by 5 days. This may push MS-003 past its target date of 10 May 2025.
Dependency #7 (MS-002 → MS-004) is broken
Negative lag of -2 days creates an impossible schedule constraint. Lead time conflicts with MS-002 current progress. Consider removing this dependency or adjusting the lag.
Critical path is valid
MS-001 → MS-002 → MS-003 → MS-005 → MS-006 (122 days total)