Cipla R&D Lab Setup PRJ-2025-001 Active
Turnkey laboratory setup project for Cipla Pharmaceuticals — R&D Division
₹1,18,50,000
Total Budget
₹28,45,000
Amount Spent
24% of budget
Jan 15 – Jun 30
Timeline (2025)
8
Team Size
3
Open Issues
2
Open Risks
Project Information
Project Code
PRJ-2025-001
Project Name
Cipla R&D Lab Setup
Customer
Project Type
Turnkey
Priority
High
Project Manager
RK
Rajesh Kumar
Description
Complete turnkey setup of Research & Development laboratory for Cipla Pharmaceuticals at their Vikhroli campus, Mumbai. The scope includes laboratory furniture, fume hoods, HVAC systems, gas piping, electrical works, and safety systems conforming to GLP/GMP standards.
Sales Owner
VJ
Vikram Joshi
Timeline
Start Date
January 15, 2025
Target End Date
June 30, 2025
Duration
167 days
Current Phase
Phase 2: Engineering Design
Phase 1
Concept
Concept
Phase 2
Engineering
Engineering
Phase 3
Procurement
Procurement
Phase 4
Installation
Installation
Phase 5
Handover
Handover
Budget Overview
Estimated Budget
₹1,18,50,000
Committed Amount
₹42,00,000
Spent Amount
₹28,45,000
Remaining
₹76,05,000
Contingency Reserve
₹11,85,000 (10% of budget)
Team Members
| Name | Role | Allocation % | Start Date | End Date | Status |
|---|---|---|---|---|---|
|
RK
Rajesh Kumar
|
Project Manager | Jan 15, 2025 | Jun 30, 2025 | Active | |
|
SI
Suresh Iyer
|
Lead Engineer | Jan 20, 2025 | Jun 15, 2025 | Active | |
|
DN
Deepak Nair
|
Site Supervisor | Feb 01, 2025 | Jun 30, 2025 | Active | |
|
PM
Priya Menon
|
Design Engineer | Jan 20, 2025 | Apr 30, 2025 | Active | |
|
AS
Amit Sharma
|
HVAC Specialist | Mar 01, 2025 | Jun 15, 2025 | Not Started | |
|
KR
Kavitha Rao
|
Procurement Lead | Feb 01, 2025 | May 31, 2025 | Active | |
|
RV
Rahul Verma
|
Electrical Engineer | Mar 15, 2025 | Jun 15, 2025 | Not Started | |
|
SG
Sneha Gupta
|
Quality & Safety | Apr 01, 2025 | Jun 30, 2025 | Not Started |
Key Milestones
Design Complete
Feb 28, 2025
Material Procurement
Mar 15, 2025 – Apr 30, 2025
Installation & Fitout
May 01, 2025 – May 31, 2025
Commissioning & Testing
Jun 01, 2025 – Jun 20, 2025
Client Handover
Jun 30, 2025
Linked Documents
Quotation
QT-2025-001
Contract
CON-2025-012
Customer Purchase Order
CIPLA/PO/2025/0034
Recent Activity
View AllRajesh Kumar updated the project budget allocation for Phase 2: Engineering Design
Today, 10:32 AM
Suresh Iyer marked milestone Design Complete as completed
Yesterday, 04:15 PM
Kavitha Rao raised a procurement risk — vendor delay for fume hood components (15 day impact)
Feb 10, 2025, 11:20 AM
Priya Menon uploaded revised lab layout drawings (Rev B) to the project documents
Feb 08, 2025, 02:45 PM
Vikram Joshi added customer PO reference CIPLA/PO/2025/0034 to the project
Feb 05, 2025, 09:00 AM